Sasmit Patra questions NALCO’s 50:50 JV with NLC India for 1,080 MW power project
Bhubaneswar, Nov 16: Biju Janata Dal (BJD) Rajya Sabha MP Dr Sasmit Patra has sought detailed explanations from National Aluminium Company Limited (NALCO) over its proposed 50:50 joint venture with NLC India Limited for setting up a 1,080 MW captive thermal power project at Angul in Odisha.
In a letter dated November 16 to NALCO Chairman-cum-Managing Director Brijendra Pratap Singh, Patra questioned the commercial viability of the proposed arrangement and asked why NALCO could not independently develop the project.
The MP pointed out that NALCO already operates a 1,200 MW captive power plant, has established infrastructure and coal linkages, and produced four million tonnes of coal from its Utkal-D and Utkal-E mines in FY 2025-26.
He sought details of whether an independent project was considered and requested a comparative techno-economic assessment of both models. He also questioned the estimated project cost, reportedly ranging between Rs 12,000 crore and Rs 17,000 crore, financing arrangements, projected electricity tariffs and expected returns.
Patra further sought clarification on the proposed coal supply arrangement from NLC India's Machhakata mine, despite NALCO's existing coal resources.
Other concerns include the valuation of land and infrastructure contributed by NALCO, its commitment to purchase 100 per cent of the electricity for 25 years despite holding only 50 per cent equity, and the sharing of financial risks and profits.
He also sought updates on project approvals, financing and implementation timelines, stressing the need for timely commissioning alongside NALCO's proposed smelter expansion by 2030-31.